A contractor has two teams of workers, team AA and team BB. Team AA can complete a project PP in 12 days and team BB can complete PP in 36 days. Team AA starts working on PP and team BB joins team AA after four days. Team AA is withdrawn after another two days and team BB is asked to double its efficiency. The number of additional days required for team BB to complete PP is

Choose one option
Answer and worked solutionTry it first, then open this to check your working.
Official answerB

Worked solution

Team AA does 112\frac1{12} of PP per day and team BB does 136\frac1{36}.

  • In the first 4 days, AA alone does 412=13\frac4{12} = \frac13.
  • In the next 2 days, together they do 2(112+136)=292\left(\frac1{12} + \frac1{36}\right) = \frac29.

Done so far: 13+29=59\frac13 + \frac29 = \frac59, so 49\frac49 remains. At double efficiency BB does 118\frac1{18} per day, so it needs 49×18=8\frac49 \times 18 = 8 more days.

(B)

Practise this topic

Every past question tagged to the same part of the syllabus, with solutions.

full papers
153
questions
13,073
worked solutions
13,054

Sit a paper tonight. See exactly where you stand.

Timed, in the real format, and marked the moment you submit.