A contractor has two teams of workers, team and team . Team can complete a project in 12 days and team can complete in 36 days. Team starts working on and team joins team after four days. Team is withdrawn after another two days and team is asked to double its efficiency. The number of additional days required for team to complete is
KVPY 2021MathematicsSingle correct+1 / -0.25
Mathematics, question 10
From KVPY 2021 · Stream SA
Answer and worked solutionTry it first, then open this to check your working.
Official answerB
Worked solution
Team does of per day and team does .
- In the first 4 days, alone does .
- In the next 2 days, together they do .
Done so far: , so remains. At double efficiency does per day, so it needs more days.
(B)
Practise this topic
Every past question tagged to the same part of the syllabus, with solutions.