Two workers AA and BB are engaged to do a piece of work. Working alone, AA takes 88 hours more to complete the work than if both worked together. On the other hand, working alone, BB would need 4124\frac12 hours more to complete the work than if both worked together. How much time would they take to complete the job working together?

Choose one option
Answer and worked solutionTry it first, then open this to check your working.
Official answerC

Worked solution

Let tt be the time together. Then AA alone takes t+8t + 8 and BB alone takes t+4.5t + 4.5, and rates add:
1t+8+1t+4.5=1t.\frac{1}{t+8} + \frac{1}{t+4.5} = \frac1t.

Multiplying out, t(t+4.5)+t(t+8)=(t+8)(t+4.5)t(t + 4.5) + t(t + 8) = (t+8)(t+4.5):
2t2+12.5t=t2+12.5t+36⇒t2=36⇒t=6.2t^2 + 12.5t = t^2 + 12.5t + 36 \Rightarrow t^2 = 36 \Rightarrow t = 6.

(The joint time is always 8×4.5=6\sqrt{8 \times 4.5} = 6 hours.)

(C)

Practise this topic

Every past question tagged to the same part of the syllabus, with solutions.

full papers
153
questions
13,073
worked solutions
13,054

Sit a paper tonight. See exactly where you stand.

Timed, in the real format, and marked the moment you submit.